Mitsubishi Electric F920GOT-K Hardware Manual page 248

Got-f900 series graphic operation terminal
Table of Contents

Advertisement

GOT-F900 SERIES (CONNECTION)
3) GT Designer
[Creation]
Operation
a)Open the GT Designer.
b)Click the [New] button.
c)Set the following.
GOT type: F940WGOT (480 × 234) <WIDE>
F94*GOT (320 × 240)
F93*GOT (240 × 80)
F920GOT(128 × 64)
PLC type: MELSEC-A
Selection of "GOT type"
GOT type
F940WGOT(480×234)<WIDE>
F94*GOT(320×240)
F93*GOT(240×80)
F920GOT(128×64)
Click [OK].
d)Set CPU direct connection (RS-422)/link connection (RS-422/RS-
232C) of the GOT-F900.
This setting is enabled in the SW4D5C-GOTR-PACKE version A
or later.
Click the check box of "Use Serial Port, Setup, Language, Menu
Key" to give a check mark ($).
Click the "Setup" tab.
Connection of MELSEC-A Series PLC 9
Model name
F940WGOT
F940GOT
Handy GOT
F930GOT-K
F930GOT
F920GOT-K
Display (screen name)
The "Select Project"
dialog box appears.
The "GOT/PLC Type"
dialog box appears.
The "Project Auxiliary
Settings" dialog box
appears..
9-18