● STILL: Measure the motor data at standstill. The inverter switches off the motor after the
motor data identification has been completed.
Select this setting if one of the following cases is applicable:
– You have selected control mode "SPD N EN", however, the motor cannot freely rotate
– You have selected V/f control as control mode, e.g. "VF LIN" or "VF QUAD".
● ROT: Measure the motor data while it is rotating. The inverter switches off the motor after
the motor data identification has been completed.
Complete quick commissioning:
Switchover the display using an arrow key: nO → YES
Press the OK key.
You have completed quick commissioning.
Converter with the CU230P-2 Control Units
Operating Instructions, 09/2017, FW V4.7 SP9, A5E34257946B AE
- for a mechanically limited travel range, for example.
5.4 Quick commissioning using the BOP-2 operator panel
Commissioning