3

First Start-up

Unpack and check the
units
Mount the unit and
install optional boards
which have not yet
been fitted
Form the DC link
capacitors, if necessary
Connect the protective
conductor, the power
cables or buses and, if
present, the ext. 24 V
supply
Connect the control
cables, communication
cables, encoder cables
and motor cables
Power up the external
24 V supply or the line
voltage
Siemens AG
6SE7087-6JP60
SIMOVERT MASTERDRIVES
www.aotewell.com
After removing the packaging, check that the unit is
intact and undamaged. Only intact units may be started
up. Please also check that the unit is complete and that
the correct optional boards are fitted.
Retrofit any optional boards which have not yet been
installed, if necessary. Then install the units taking into
account the requirements at the point of installation and
the EMC instructions.
If the DC link of the unit was de-energized for more than
one year, you have to newly form the DC link capacitors
Please connect, starting with the protective conductor,
the power cables or DC link buses and, if present, the
external 24 V supply. Pay attention to EMC instructions
when laying the cables. Please do not at this stage
connect any control, communication, encoder and motor
cables (exception: cable for connecting up an OP1S, if
parameterization is to be effected via the OP1S).
Please connect the remaining control, communication,
encoder and motor cables. Pay attention to the EMC
instructions when laying the cables.
WARNING
The device must be disconnected from
its voltage supplies (24 V DC electronics
supply and DC link / mains voltage)
before the control and encoder leads are
connected or disconnected!
Failure to observe this advice can result in
encoder defects, which may in turn cause
uncontrolled axis movements.
After checking that the cabling has been correctly
connected and that it sits properly, power up the
external 24 V supply or the line voltage. After the
electronics power supply has been started, the unit
initializes itself. The action can take several seconds.
The drive status is subsequently shown on the PMU.
Operating Instructions
sales@aotewell.com
Industry Automation
First Start-up
See section
"Transport,
Storage,
Unpacking"
See section
"Installation"
and "Installation
in Conformance
with EMC
Regulations"
See section
"Forming"
See section
"Connecting-up"
and
"Installation in
Conformance
with EMC
Regulations"
See section
"Connecting-up"
and "Installation
in Conformance
with EMC
Regulations"
111
3-1
+86-755-8660-6182

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents