Commissioning

5.1

Commissioning ET 200eco PN

Introduction
Your automation system is commissioned depending on the current plant configuration. The
section below describes the procedure for commissioning the ET 200eco PN on an IO
Controller.
Requirements for commissioning the ET 200eco PN on the PROFINET IO
Actions
ET 200eco PN installed
ET 200eco PN wired
The IO Device was assigned a device name
ET 200eco PN configured
Supply voltage for the IO Controller is switched on
IO Controller switched to RUN
Commissioning ET 200eco PN
1. Switch on the voltage supply 1L+ non-switched for the ET 200eco PN.
2. Switch on the supply voltage(s) 2L+ switched as required.
ET 200eco PN
Operating Instructions, 08/2016, A5E01250250-AJ
Reference
Chapter Installing (Page 20)
Chapter Wiring (Page 29)
Chapter Configuring (Page 67)
Chapter Configuring (Page 67)
IO Controller manual
IO Controller manual
5
77

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents