Cabinet Installation
The installation of the pre-loaded cabinets consist of the following steps:
1. Move the cabinet to installation site.
2. Lower the leveling feet. (This will prevent excessive wear on the casters.)
3. Connect the system console to the server.
4. Connect all user terminals to the server.
5. Connect all system peripherals to the server.
NOTE
Attaching cables while the rails are extended fully forward will ensure
sufficient slack for later maintenance.
6. Connect the cabinet power cord to the appropriate wall outlet.
If the cabinet being installed contains a PowerTrust UPS option, perform the
NOTE
steps under PowerTrust UPS Option.
7. Be sure all peripherals outside the cabinet are connected to wall outlets.
The cabinet/server system assembly is now ready for the power up process. Refer to
Chapter 4 for operating instructions.
Chapter 2
Unpacking and Installation
Cabinet Installation
2-7