5 DATA USED FOR POSITIONING CONTROL
Setting item
Cd.27 Step mode
Cd.28 Step start information
Cd.29 Skip command
Cd.30 New torque value
Cd.31 Positioning starting point No.
When using step operation, set which unit to step with.
When using step operation, set whether to continue or restart operation.
Set "1" to skip the current positioning.
To change the " Md.45 Torque limit stored value", set the new estimated torque
limit stored value.
Set the value within the " Pr.18 Torque limit setting value" range.
Set the "start point No. (1 to 50)" for executing block start (positioning).
(If setting the value other than 1 to 50, process it as "1".)