C.7 LOGICAL NODES
Table C–1: IEC 61850 LOGICAL NODES (Sheet 4 of 4)
NODES
TPOS: Position indicator
TPRS: Pressure sensor
TRTN: Rotation transmitter
TSND: Sound pressure sensor
TTMP: Temperature sensor
TTNS: Mechanical tension
TVBR: Vibration sensor
TVTR: Voltage transformer
TWPH: Water acidity
C
X: LOGICAL NODES FOR SWITCHGEAR
XCBR: Circuit breaker
XSWI: Circuit switch
Y: LOGICAL NODES FOR POWER TRANSFORMERS
YEFN: Earth fault neutralizer (Petersen coil)
YLTC: Tap changer
YPSH: Power shunt
YPTR: Power transformer
Z: LOGICAL NODES FOR FURTHER POWER SYSTEM EQUIPMENT
ZAXN: Auxiliary network
ZBAT: Battery
ZBSH: Bushing
ZCAB: Power cable
ZCAP: Capacitor bank
ZCON: Converter
ZGEN: Generator
ZGIL: Gas insulated line
ZLIN: Power overhead line
ZMOT: Motor
ZREA: Reactor
ZRES: Resistor
ZRRC: Rotating reactive component
ZSAR: Surge arrestor
ZSCR: Semi-conductor controlled rectifier
ZSMC: Synchronous machine
ZTCF: Thyristor controlled frequency converter
ZTRC: Thyristor controlled reactive component