Result
The complete PLC program is downloaded to the device. Blocks that only exist online in the
device are deleted. By downloading all affected blocks and by deleting any blocks in the
device that are not required, you avoid inconsistencies between the blocks in the user
program.
The messages under "Info > General" in the Inspector window indicate whether the
download was successful.
3.7
Commissioning software controller
Procedure
To open the "Commissioning" work area of the technology object, follow these steps:
1. Open the "Technology objects" folder in the project tree.
2. Open the technology object in the project tree.
3. Double-click the "Commissioning" object.
The commissioning functions are specific for each controller and are described there.
3.8
Save optimized PID parameter in the project
The software controller is optimized in the CPU. Through this, the values in the instance-DB
on the CPU no longer agree with those in the project.
To update the PID parameter in the project with the optimized PID parameters, proceed as
follows:
Requirement
● An online connection to the CPU is established and the CPU is in "RUN" mode.
● The functions of the commissioning window have been enabled by means of the "Start"
button.
Procedure
1. Open the CPU folder in the project tree.
2. Open the "Technology objects" folder.
3. Open a technology object.
4. Double click on "Commissioning".
5. Click on the
6. Save the project.
Result
The currently active PID parameters are stored in the project data. When reloading the
project data in the CPU, the optimized parameters are used.
PID control
Function Manual, 03/2017, A5E35300227-AC
icon "Upload PID parameters".
Configuring a software controller
3.7 Commissioning software controller
45