Commissioning
Commissioning
completed
Fault 420
28
Commissioning is completed when the following message is
displayed.
Confirm the message with OK.
The machine is now ready for use.
The settings made during the commissioning process are only
adopted after a complete program has been run.
Select any program, e.g.:
Press the Start/Stop button to start the program.
After commissioning, every program starts with reactivation of the
water softener.
If the program is canceled using
connections are deactivated.
Confirm the error message with OK.
Use the button to switch the machine off.
Wait approximately 10 seconds before switching the machine on
again with the button.
The commissioning procedure starts again.
Perform commissioning and activate at least one plumbing
connection; e.g. for cold water.
Set up successful
Normal plus
Temperature
75 °C
Duration
1:30
Drain
.
Fault 420
h
, all the plumbing