Procedure
1.
Power down the compute module.
2.
Remove the compute module.
3.
Place the compute module on a flat, level work surface.
4.
Remove the access panel.
5.
Locate the appropriate mezzanine connector. To locate the connector, see the "System board
components."
6.
Remove the mezzanine connector cover, if installed.
7.
Install the mezzanine card. Press firmly on the PRESS HERE label above the mezzanine connector to
seat the card.
When a GPU mezzanine adapter is installed in the compute module, an additional mounting bracket is
required.
Type C
8.
Install the access panel.
9.
Install the compute module.
10. Power up the compute module.

Installing the HPE Smart Array P542D Controller mezzanine option

IMPORTANT:
For more information about the association between the mezzanine bay and the interconnect bays, see
the HPE Synergy 12000 Frame Setup and Installation Guide in the Hewlett Packard Enterprise
Information Library (http://www.hpe.com/info/synergy-docs). Where you install the mezzanine card
determines where you need to install the interconnect modules.
To install the component:
Procedure
1.
Power down the compute module.
2.
Remove the compute module.
3.
Place the compute module on a flat, level work surface.
4.
Remove the access panel.
5.
Locate the appropriate mezzanine connector. To locate the connector, see System board components.
6.
Remove the mezzanine connector cover, if installed.