Siemens SINAMICS S120 Installation And Start-Up Manual page 52

Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

Commissioning
Creating a project in STARTER
Table 3-3
Search sequence in STARTER (example), continued
What to do?
3. Add drive
Here, you can search for nodes that can be accessed.
units
4. Summary
You have now created the project.
–>
Click "Complete".
5. Configure the
Once you have created the project, you have to configure the drive unit.
drive unit
The following sections provide some examples.
3-52
How to do it?
SINAMICS S120 Installation and Start-Up Manual, 12/04 Edition
Comments
E Siemens AG, 2004. All rights reserved

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents