LG's ACP BACnet Agreement
JMT (Joint Matching Test)
This is necessary for every independent BMS.
The case where a JMT is not necessary is where previously a successful JMT has been carried out
and the BMS system has not been updated by software or hardware changes. In the case that the
BMS has updated their system by either changes, a following JMT will be required.
ACP BACnet Diagnosis
Use of LG's ACP BACnet setup-tool is for confirming the operation/state of connected A/C units &
address ID's, prior to connection with the BMS system.
BMS Engineering
Creating of the Points. This is NOT to be done by LG since it is directly related to the BMS side. The
BMS engineer is to carry out the engineering of the Point, however LG is responsible for providing
the method of how the Points are calculated.
Commission
First step, only using LG's ACP BACnet, without connecting BMS. This is to be carried out by LG
engineering staff with the use of the ACP BACnet set up tool.
Discrepancy of operation of Gateway by BMS
In the case that the BMS maker feels that the ACP BACnet is not functioning correctly via the
BACnet Protocol, a test with the use of LG's ACP BACnet Client software can confirm this. (This test
is generally not required)
LG's ACP BACnet Agreement