DLP-G32 Install the Y-Cable Protection Modules
Step 2
Insert the appropriate module into the FlexLayer shelf assembly.
Note
Use a Phillips screwdriver to install the two accompanying screws.
Step 3
Figure 1-29
Figure 1-29
Splitter/Coupler Modules, and/or
Repeat this task as necessary for each FlexLayer module you want to install.
Step 4
Return to your originating procedure (NTP).
Step 5
DLP-G32 Install the Y-Cable Protection Modules
Purpose
Tools/Equipment
Prerequisite Procedures None
Required/As Needed
Onsite/Remote
Security Level
Determine the Y-cable modules that you want to install in the FlexLayer shelf.
Step 1
Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
1-70
FlexLayer modules are not listed in generated Cisco MetroPlanner 2.5 site plans.
shows the FlexLayer shelf assembly and how the FlexLayer modules can be installed.
ONS 15xxx FlexLayer Shelf Assembly
Add/Drop Modules,
Protection Modules
VOA Module
This task installs the Y-cable protection modules in the FlexLayer shelf
assembly.
#2 Phillips screwdriver
Y-Cable modules:
As needed
Onsite
None
Chapter 1
Shelf assembly
Frame Ground Terminal
Fiber Management Tray
Multi-Mode Y Cable Protection FlexMod: 15216-CS-MM-Y=
Single-Mode Y Cable Protection FlexMod: 15216-CS-SM-Y=
Install the Shelf and Common Control Cards