Dimm Installation Sequence - IBM NeXtScale nx360 M4 Installation And Service Manual

Hide thumbs Also See for NeXtScale nx360 M4:
Table of Contents

Advertisement

Operator information
panel
Figure 56. DIMM connectors location

DIMM installation sequence

Depending on the server model, the server may come with a minimum of one 4
GB DIMM installed in slot 4. When you install additional DIMMs, install them in
the order shown in the following table to optimize system performance.
In general, all channels on the memory interface for each microprocessor can be
populated in any order and have no matching requirements.
136
IBM NeXtScale nx360 M4 Type 5455: Installation and Service Guide
DIMM 4
PCI riser
connector 2
DIMM 7
DIMM 8
Microprocessor 2
10GB ethernet
card connector
Power distribution
DIMM 3
board connector
DIMM 2
DIMM 1
Microprocessor 1
DIMM 6
DIMM 5
USB hypervisor key
3V lithium battery
SATA connector
LED signal connector
PCI riser
connector 1