GE SG Series Installation Manual page 25

Hide thumbs Also See for SG Series:
Table of Contents

Advertisement

SG Series 10 & 20
How to access the terminals for the cable connections.
To access input, output and Battery connections proceed as follows:
 Remove protection panel "A".
 Remove protection panel "B".
 Remove UPS side panel "C".
 Only for Dual Input Utility:
Remove with appropriate tool the metallic window "D" from the metal screen "C".
Modifications reserved
GE_UPS_OPM_SGS_ISG_10K_40K_0US_V070.docx
Top entry cables
E
Bottom entry cables
Fig. 3.8.1-1 Access to the input / output connections of SG Series 10 & 20
Critical Power
Please remove the plate "E & F"
!
before drilling any wholes.
A
D
F
C
B
Page 25/46