PART 8. POWER UP PROCEDURES
This section describes items to check before starting the OfficeServ 7100 system and the
procedure for starting the system.

8.1 PRE-CHECK

This section describes items to check before starting the OfficeServ 7100 system.
8.1.1 Safety Precautions
• Temperature: Check if the temperature of the room where the system is installed is
between 32°F and 113°F. If the room temperature is higher or lower than the normal
operation temperature, install a heating/cooling device to maintain normal temperature.
• Humidity: Check if the room humidity where the system is installed is between 10% and
90%. Take special caution since humidity affects the electrical components and
connectors of the system.
• Direct sunlight and dust: The room where the OfficeServ 7100 system is installed should
be protected from direct sunlight and should have ventilation systems to prevent the
system from malfunctioning due to dust.
8.1.2 Safety Conditions
The building where the OfficeServ 7100 system is installed should have lightning rods and
grounding to protect the system against lightning and electric leakage.
• Check if the OfficeServ 7100 system is not inclined and is maintained horizontally.
• Do not place devices that may cause electromagnetic interference near the system.
• Place a fire extinguisher near the system.
• Check if the AC voltage switch of the PSU is properly set to 110VAC power.
• Check if the grounding terminal on the rear panel of the system is properly connected to
the external grounding.
8.2a STARTING THE SYSTEM (MP10)
The procedure for starting the OfficeServ 7100 system is as follows:
1)
Check if the cards and cables are properly mounted and connected to the OfficeServ
7100 cabinet.
2)
Make sure the MP10 MMC+/SD Card with system software is in the Media slot.
3)
Make sure the memory backup switch on MP10 is in the ON position.
4)
Turn on the power of the OfficeServ 7100 cabinet.
5)
Check the LEDs of the MP10.