Mitsubishi Electric AE-200A Installation Manual page 28

Hide thumbs Also See for AE-200A:
Table of Contents

Advertisement

(2) System with connection to one or more AE-50 controllers
(controlling more than 50 units of equipment)
AE-200
Cable tie
TB1
TB3
(~100-240V)
(M-NET)
L/L1 N/L2
A
B
S
M-NET transmission cable S (Shield)
AC power cables (Polarized)
Note
● The M-NET power jumper (CN21) needs to be connected or disconnected, depending on the system configuration. Refer to
chapter 5 "System configuration" for details.
● Make the protective ground wire longer than the AC power cables (L/L1, N/L2). (Approximately 40 mm (1-37/64 in))
● Use M3.5 ring terminals to connect the cables to the terminal blocks.
● Use an M4.0 ring terminal to connect the protective ground wire.
● Properly fix the cable sheaths in place with the supplied cable ties. The distance between the sheath end and the ring
terminal must be 30 mm (1-3/16 in) or less.
WT07137X01
M-NET transmission cables
for centralized control
AC power cables (Polarized)
Overcurrent breaker
Earth leakage
breaker
Power supply
100–240 VAC
50/60 Hz
AC power cables (Polarized)
Switching
HUB
M-NET transmission cables A and B
(Non-polarized)
Outdoor unit
TB7
Overcurrent breaker
Earth leakage breaker
AE-50
M-NET transmission cables
for centralized control
TB1
TB3
(~100-240V)
(M-NET)
L/L1 N/L2
A
B
S
AC power cables (Polarized)
28
Power supply
100–240 VAC
50/60 Hz
M-NET transmission cables A and B
(Non-polarized)
M-NET transmission cable S (Shield)
Outdoor unit
TB7

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ae-50aAe-200eAe-50e

Table of Contents