Smart-UPS
®
VT and
MGE™ Galaxy™ 3500
Maintenance Bypass Panel
with Power Distribution
(wall-mount)
10-30 kVA
208 V

Summary of Contents

  • Page 1

    Installation Smart-UPS ® VT and MGE™ Galaxy™ 3500 Maintenance Bypass Panel with Power Distribution (wall-mount) 10-30 kVA 208 V...

  • Page 3: Table Of Contents

    Contents Safety ... 1 SAVE THESE INSTRUCTIONS ....... 1 Safety warnings ......... 1 Live maintenance precautions .

  • Page 5: Safety, Save These Instructions, Safety Warnings

    This UL-listed unit was designed to operate in conjunction with the Smart-UPS VT and MGE Galaxy 3500 10-30kVA, 208V UPS. Safety warnings Warning: Only APC by Schneider -trained personnel who are familiar with the construction and operation of this equipment, as well as the mechanical and electrical hazards involved, may perform this installation.

  • Page 6: Live Maintenance Precautions

    APC does NOT recommend performing live maintenance to the MBP with Power Distribution. However, APC is aware that due to the critical nature of data center loads, live maintenance may occur. If providing live maintenance, observe the following precautions to reduce the risk of electrical shock.

  • Page 7: Product Overview, Features

    Product Overview Features The wall-mount version of the Smart-UPS VT and MGE Galaxy 3500 MBP combines bypass functionality with power distribution capability in a common enclosure.The lower section of the MBP contains switches that facilitate the transfer of power from the UPS to bypass operation to allow maintenance to be performed on the UPS.

  • Page 8: Internal Components

    Internal components Neutral Bar Cable Connection Ground Bar Neutral Bar Strain-relief Bar Fuse Block ([3]90A Fuses) Ground Terminal Compression Lug Power Terminal Block UPS Inputs Q1 Switch Smart-UPS® VT and MGE™ Galaxy™ 3500 10-30 kVA 208 V MBP Installation Panel Board (42-position) Ground Bar Neutral Bar Strain-relief Bar...

  • Page 9: Schematic

    Schematic Smart-UPS® VT and MGE™ Galaxy™ 3500 10-30 kVA 208 V MBP Installation...

  • Page 10: Considerations, Environmental

    Considerations Environmental • The wall area selected for the MBP installation must be structurally sound and able to accommodate the size and weight of the unit. Refer to “Mounting the MBP” on page 9. • The MBP should be kept in a climate-controlled environment having a temperature range of 0° to 40°C [32°...

  • Page 11: Installation, Overview, Tools, Panel Board Breakers

    • Level • Marker • Drill Panel board breakers The 42-position panel board supports the following Square D breakers. All of the circuit breakers listed below have been pre-tested and approved by APC. Breaker Type 1-pole, 20Amp 2-pole, 20Amp 2-pole, 30Amp Smart-UPS®...

  • Page 12: Removing The Front Door (optional)

    Removing the front door (optional) Note: Front door removal is NOT a requirement for this installation. However, removing the door will allow better access to the internal components. 1. Place the MBP on its back such that its front door is facing straight up. 2.

  • Page 13: Mounting The Mbp

    Mounting the MBP APC by Schneider Electric recommends mounting the MBP to 3/4 inches plywood backing (36 in [914mm] high x 28 in [711mm] wide). 1. Attach the 3/4 inches plywood securely to the designated wall area. The wall should be strong enough to support the 120lb [54.5kg] MBP.

  • Page 14: Internal Cable Connections

    Internal cable connections For the convenience of the installer, ALL internal MBP cable connections were made prior to shipment. Check to make certain the following internal cable connections were completed: • Power Terminal Block [L1, L2, L3, N, top-to-bottom] to Input Bus [L1, L2, L3, N, top-to- bottom] •...

  • Page 15: Making External Cable Connections

    Making external cable connections Note: Utility cables can enter through the top or the bottom of the MBP. However, BOTTOM is recommended. External cables can enter the MBP through any of the available 1-inch [25.4mm] knockouts, or by making larger cutouts in the top or bottom plates of the enclosure. Each plate offers 22 knockouts and the ability to create up to four (4) 2-inch [50.8mm] cutouts.

  • Page 16

    UPS connections. Note: UPS cables can enter through the top or the bottom of the MBP. However, BOTTOM is recommended. Refer to the Smart-UPS VT 10-30kVA or MGE Galaxy 3500, 208V Installation Manual for MBP cable connections at the UPS. 1.

  • Page 17: Re-attaching The Front Door

    Re-attaching the front door Note: This section applies only if the front door was removed at the start of the installation process. If you chose not to remove the door, ignore this section. Re-attaching the front door requires at least two people: one to hold the door in place, and the other to make the necessary hardware connections.

  • Page 18: Installing Panel Board Breakers

    Installing Panel Board Breakers This section describes how to install breakers to the MBP’s 42-position panel board. Electrical Hazard: Before installing breakers, make sure ALL MBP switches are in the OFF position. From normal operation, first switch Q2 OFF, and then switch Q1 OFF. 1.

  • Page 19: Appendix A: Changing Fuses, Removing Fuses, Replacing Fuses

    Appendix A: Changing Fuses Warning: Before changing fuses, make sure ALL MBP switches are in the OFF position. From normal operation, first switch Q2 OFF, and then switch Q1 OFF. Note: Replace ALL blown fuses with Bussmann “Class J” 90 Amp fuses (p/n JKS-90). Removing fuses 1.

  • Page 24

    APC Worldwide Customer Support Customer support for this or any other APC product is available at no charge in any of the following ways: • Visit the APC Web site to access documents in the APC Knowledge Base and to submit customer support requests.