g

4.5.6.3 Notes concerning use / maintenance of a parallel system

ECO-mode:
If LP-U units operate in parallel, the ECO-mode feature is not available.
No-load shutdown:
If LP-U units operate in parallel, the no-load shutdown function is not available.
Manual bypass:
If you want to switch one of the UPSs to bypass operation using the manual bypass switch (switch
is turned into position 2) then all UPSs in the parallel system have to be switched to bypass
operation in order to prevent damage.
Maintenance:
To isolate a unit from the redundant system:
1. Switch off the UPS which has to be isolated,
2. Remove the installation fuse from the input of that UPS (F1-4 in figure 17),
3. Separate the output of the UPS from the output junction (S1-4 in figure 17).
To re-enter the unit into the system:
4. Reinstall the installation input fuse,
5. Connect the output of the UPS to the output junction,
6. Switch on the UPS.
LX: OPM_LPU_11U_5K0_10K_1US_V030
Digital Energy
21
GE DE LP 11U UPS: Installation / User Manual 3.0 (US)
LP Series

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents