5. Insert Tube 1 into rubber elbow drain port and secure with a
silver hose clamp. Angle tube outward toward front of
furnace.
6. Cut 17 7/8 inches from the long end of Hose B and discard.
7. Secure remaining end of Hose B to exposed end of Tube 1
with a green hose clamp. Route hose toward right side
panel grommet holes.
8. Insert short end of one Tube 2 through rear right side panel
grommet drain hole. Secure tube to Hose A with a green
hose clamp.
9. Insert short end of remaining Tube 2 into Hose B from
rubber elbow and secure with green hose clamp. Ensure
hoses and tubes maintain a downward slope for proper
drainage and are not kinked or binding.
For details concerning mounting of the drain trap, refer to the fol-
lowing section.
U
D
T
M
(L
R
S
P
)
PRIGHT
RAIN
RAP
OUNTING
EFT OR
IGHT
IDE
ANEL
1. Insert drain tubes into drain trap and position the drain trap
against the side panel. NOTE: Drain tubes must reach the
bottom of the drain trap.
2. Secure drain trap to side panel at the mounting holes
(dimples or crosshairs) located below the grommet drain
holes.
3. Attach PVC drain line to drain trap outlet with either a 90°
elbow or coupling.
H
I
ORIZONTAL
NSTALLATIONS
NOTE: This furnace is shipped from the factory as a Dedicated
Upflow. A “Blocked Drain Kit” is available and MUST BE USED if the
furnace is installed Horizontal Left or Horizontal Right. Check the
Serial/ Rating Plate on the furnace for the Kit P/N.
R
S
D
IGHT
IDE
OWN
WARNING
A
BLOCKED DRAIN KIT IS REQUIRED FOR HORIZONTAL
. T
INSTALLATIONS WITH THE RIGHT SIDE OR LEFT SIDE DOWN
HE KIT
. F
PROTECTS AGAINST A BLOCKED CONDENSATE DRAIN
AILURE TO
PROPERLY INSTALL THE KIT COULD LEAD TO BODILY INJURY OR
.
DEATH DUE TO CARBON MONOXIDE EXPOSURE
NOTE: This furnace is shipped from the factory as a Dedicated
Upflow. A “Blocked Drain Kit” is available and MUST BE USED if the
furnace is installed Horizontal Left or Horizontal Right. Check the
Serial/ Rating Plate on the furnace for the Kit P/N.
Horizontal installations with the right side down require that the
drain hoses be connected to the right side front cover drain port
and the rubber elbow drain port.
Make connections as follows:
1. Remove the rubber plug/cap from the coil front cover drain
port.
2. Secure Hose A to front cover drain tap with a red hose clamp.
Route hose to rear right (down) side panel grommet holes.
3. Cut 1/4 inch from the end of the drain port on the rubber
elbow and discard.
4. Insert Tube 1 into rubber elbow drain port and secure with a
silver hose clamp. Angle tube outward toward front of furnace.
5. Cut 17 3/4 inches from the long end (end opposite the bend)
of Hose B. Save the part with the bend and discard the
17 3/4 inch piece that was cut.
6. Secure remaining end of Hose B to exposed end of Tube 1
with a green hose clamp. Route hose to front right down
side panel grommet holes.
7. Cut 5 1/2 inches straight length from the long end (end with
taper) of each Tube 2. Save the 5 1/2” long pieces and
discard the pieces with the bends.
8. Insert approximately one inch of each Tube 2 through the
right down side panel grommet holes. Secure tubes to
Hose A and Hose B using green hose clamps. Ensure
hoses and tubes maintain a downward slope for proper
drainage and are not kinked or bound.
9. A “Blocked Drain Kit” MUST be installed for right side down
installations. The kit includes a front cover pressure switch
that must be used to protect against a blocked drain
condition. Install the front cover pressure switch per the
instructions included with the “Blocked Drain Kit”. Failure to
install the “Blocked Drain Kit” will void the warranty and could
lead to bodily injury or death.
For details concerning mounting of the drain trap, refer to Section
X, Condensate Drain Lines and Drain Trap - Horizontal Drain Trap
Mounting (Left or Right Side Panel).
L
S
D
EFT
IDE
OWN
WARNING
A
BLOCKED DRAIN KIT IS REQUIRED FOR HORIZONTAL
. T
INSTALLATIONS WITH THE RIGHT SIDE OR LEFT SIDE DOWN
HE KIT
. F
PROTECTS AGAINST A BLOCKED CONDENSATE DRAIN
AILURE TO
PROPERLY INSTALL THE KIT COULD LEAD TO BODILY INJURY OR
.
DEATH DUE TO CARBON MONOXIDE EXPOSURE
NOTE: This furnace is shipped from the factory as a Dedicated
Upflow. A “Blocked Drain Kit” is available and MUST BE USED if the
furnace is installed Horizontal Left or Horizontal Right. Check the
Serial/ Rating Plate on the furnace for the Kit P/N.
Horizontal installations with the left side panel down will require
drain hoses to be connected to the left side front cover drain port
and the side drain port on the rubber elbow.
1. Remove the rubber plug/cap from the coil front cover left
(down) side drain port.
2. Secure Hose A to front cover drain port with a red hose
clamp. Route hose to rear left (down) side panel grommet
holes. NOTE: For left side drainage, grommets must be
relocated to left side panel.
3. Remove the rubber cap from the side drain port on the rubber
elbow.
4. Secure the short end of Hose B to rubber elbow side drain
port using a green hose clamp. NOTE: For left side drainage,
route hose to far left (down) side panel grommet holes.
NOTE: Horizontal left side connections (when using new
side port drain elbow) does not require connecting a hose
to the induced draft blower housing.
5. Cut 5 1/2 inches straight length from the long end (end with
taper) of each Tube 2. Save the 5 1/2” long pieces and
discard the pieces with the bends.