a. Install drain tube coupling (factory-supplied in loose
parts bag) into collector box drain tube (blue label)
which was previously connected to condensate trap.
b. Connect large diameter drain tube and clamp (factory-
supplied in loose parts bag) to drain tube coupling,
extending collector box drain tube.
c. Route extended tube (blue label) to condensate trap and
cut to appropriate length.
d. Clamp tube to prevent any condensate leakage.
2. Inducer Housing Drain Tube
a. Remove and discard LOWER (molded) inducer housing
drain tube which was previously connected to conden-
sate trap.
b. Use inducer housing drain extension tube (violet label
and factory-supplied in loose parts bag) to connect
LOWER inducer housing drain connection to conden-
sate trap.
c. Determine appropriate length, cut, and connect tube.
d. Clamp tube to prevent any condensate leakage.
3. Relief Port Tube
a. Extend collector box tube (green label) which was
previously connected to condensate trap by splicing to
small diameter tube (factory-supplied in loose parts bag).
b. Route extended collector box pressure tube to relief port
connection on condensate trap.
c. Determine appropriate length, cut, and connect tube.
d. Clamp tube to prevent any condensate leakage.
AUXILIARY "J" BOX
CONDENSATE
TRAP
RELOCATE TUBE BETWEEN BLOWER SHELF AND INDUCER HOUSING FOR
PLUG
CAP
COLLECTOR BOX
EXTENSION TUBE
COLLECTOR
BOX EXTENSION
DRAIN TUBE
DRAIN TUBE COUPLING
COLLECTOR BOX TUBE (PINK)
060, AND 080 HEATING INPUT FURNACES
Fig. 11—Horizontal Left Tube Configuration
—10—
C. Condensate Trap Field Drain Attachment
Refer to Condensate Drain section for recommendations and
procedures.
D. Pressure Switch Tubing
The LOWER collector box pressure tube (pink label) is factory
connected to the High Pressure Switch for use when furnace is
installed in UPFLOW applications. This tube MUST be discon-
nected, extended, rerouted, and then reconnected to the pressure
switch in HORIZONTAL LEFT applications for 060 and 080
heating input furnaces.
NOTE: See Fig. 11 or tube routing label on main furnace door to
check for proper connections.
Modify tube as described below.
1. Disconnect collector box pressure tube (pink label) attached
to High Pressure Switch.
2. Use smaller diameter tube (factory-supplied in loose parts
bag) to extend tube disconnected in item 1.
3. Route extended tube:
a. Behind inducer housing.
b. Between blower shelf and inducer housing.
4. Determine appropriate length, cut, and reconnect tube to
High Pressure Switch connection labeled COLLECTOR
BOX.
E. Condensate Trap Freeze Protection
Refer to Condensate Drain Protection section for recommenda-
tions and procedures.
F. Construct a Working Platform
Construct working platform where all required furnace clearances
are met. (See Fig. 3 and 12.)
COLLECTOR BOX
DRAIN TUBE
(BLUE AND WHITE STRIPED)
COLLECTOR BOX
TUBE (GREEN)
INDUCER HOUSING
DRAIN TUBE (VIOLET)
COLLECTOR BOX
DRAIN TUBE (BLUE)
A02288