7-3. Connecting the Signal Lines

• Separately procure items such as terminal blocks and cables locally.
• The maximum wire length is 100 m. However, since the use of long wires makes the device susceptible to
noise, using wires shorter than 10 m is recommended.

(1) Pulse input (non-voltage a contact)

* To use these, various settings need to be configured. Refer to "8 Initial Setting Procedure".
24 VDC
CN 10
/
11
Ch1
Ch2
+
+
Example:
Watthour
Water
meter
meter
/
19
/
20
Ch3
Ch4
+
+
Gas
Calorimeter
meter
Note:
• The pulse weight can be added to each of the inputs of
channels 1 to 4.
For details, refer to "9 Switch List".
• This device does not support level meters.
To use a level meter, incorporate a Converter circuit
externally and convert to pulse input.
Caution:
• The polarity of the input terminals is important, so be sure to
match the polarity when using contacts that have polarity.
• Select a contact with a minimum applicable load of 1 mA or
less.
• Supply 24 VDC 1 mA from the positive terminal to the
contacts of the meters.
• The pulse unit of the watt-hour meter being used should be
Line
Onsite
1 kWh/pulse or less. Note that the apportioning error will
increase if a watt-hour meter with large pulse unit is used.
• Strip 12±1 mm (15/32 ±1/32 in) of the wire coating and insert
firmly into the terminal.
• Make sure that the copper wiring is not short-circuiting the
plates (cover, lower case) or neighboring wires.
• Perform wiring so that the terminal block is not strained.
If strained, use a wire guide or junction terminal to alleviate
the stress on the terminal block.
8

Advertisement

Table of Contents
loading

Table of Contents